Sobes.tech
Senior — Principal

How to calculate SV and SPI?

sobes.tech AI

Answer from AI

SV (Schedule Variance) and SPI (Schedule Performance Index) are key indicators in project management methodology based on Earned Value Management (EVM).

  • Schedule Variance (SV) shows the deviation from the schedule and is calculated as the difference between the earned value (EV) and the planned value (PV):

    SV = EV - PV
    

    If SV > 0 — the project is ahead of schedule, if SV < 0 — it is behind.

  • Schedule Performance Index (SPI) is the schedule performance index, showing the efficiency of time utilization:

    SPI = EV / PV
    

    If SPI > 1 — the project is progressing faster than planned, if SPI < 1 — slower.

Example:

If currently planned to perform work worth 100 thousand rubles (PV), and actually performed work worth 90 thousand rubles (EV), then:

SV = 90,000 - 100,000 = -10,000 (delay)
SPI = 90,000 / 100,000 = 0.9 (efficiency below 1)
How to calculate SV and SPI? — Project Manager - sobes.tech