How does contingency differ from management reserve?

sobes.tech AI

Answer from AI

Contingency reserve and management reserve are two different types of reserves in project management related to risks and uncertainties.

  • Contingency reserve

    • Intended for known risks that may occur in the project.
    • The size of the reserve is calculated based on risk analysis and included in the project plan.
    • Used to cover costs if known risks materialize.
  • Management reserve

    • Intended for unforeseen, unknown risks and changes that were not considered in planning.
    • Usually controlled by the project's top management.
    • Used at the project manager's discretion for unforeseen situations.

Example: If there is a risk of delivery delay in the project, a contingency reserve is allocated for it. If a completely new problem arises that was not considered in the risks, a management reserve can be used to address it.