What is EAC and its formulas?

sobes.tech AI

Answer from AI

EAC (Estimate at Completion) — is the projected total cost of the project at its completion, considering current costs and progress.

Main formulas for EAC:

  1. If it is assumed that future costs will follow the plan:
EAC = BAC / CPI

where:

  • BAC (Budget at Completion) — the budget for project completion
  • CPI (Cost Performance Index) — the cost efficiency index (EV / AC)
  1. If it is assumed that future costs will follow current efficiency:
EAC = AC + (BAC - EV)
  1. If both cost and schedule efficiencies are considered:
EAC = AC + [(BAC - EV) / (CPI * SPI)]

where:

  • AC (Actual Cost) — actual costs
  • EV (Earned Value) — earned value
  • SPI (Schedule Performance Index) — schedule performance index

The choice of formula depends on assumptions about the project's future course.