What is EAC and its formulas?
sobes.tech AI
Answer from AI
EAC (Estimate at Completion) — is the projected total cost of the project at its completion, considering current costs and progress.
Main formulas for EAC:
- If it is assumed that future costs will follow the plan:
EAC = BAC / CPI
where:
- BAC (Budget at Completion) — the budget for project completion
- CPI (Cost Performance Index) — the cost efficiency index (EV / AC)
- If it is assumed that future costs will follow current efficiency:
EAC = AC + (BAC - EV)
- If both cost and schedule efficiencies are considered:
EAC = AC + [(BAC - EV) / (CPI * SPI)]
where:
- AC (Actual Cost) — actual costs
- EV (Earned Value) — earned value
- SPI (Schedule Performance Index) — schedule performance index
The choice of formula depends on assumptions about the project's future course.