What is three-point estimation?
sobes.tech AI
Answer from AI
Three-point estimation is a method of estimating the time or resources required to complete a task based on three values:
- Optimistic estimate (O) — the minimum time in which the task can be completed under ideal conditions.
- Pessimistic estimate (P) — the maximum time that might be needed, considering possible problems.
- Most likely estimate (M) — the most realistic time to complete the task.
The expected time (E) is calculated using these three estimates with the formula:
E = (O + 4M + P) / 6
This approach helps account for uncertainty and risks in planning, making estimates more accurate and justified. It is often used in project management for scheduling and deadline estimation.