What is the Schedule Performance Index (SPI)?

sobes.tech AI

Answer from AI

Schedule Performance Index (SPI) is a measure of project schedule efficiency. It indicates how the actual progress compares to the planned progress at a given point in time.

Formula:

SPI = Earned Value (EV) / Planned Value (PV)
  • EV (Earned Value) — the cost of work actually performed to date.
  • PV (Planned Value) — the budgeted cost of work scheduled to be performed to date.

If SPI = 1, the project is on schedule. If SPI < 1, the project is behind schedule. If SPI > 1, the project is ahead of schedule.

Example: if 50% of the project time has passed and 40% of the work cost has been completed, then SPI = 0.8 — meaning the project is behind schedule.